PROJECT MANAGEMENT

Customer RFQ                                                               
Request for quotation with product drawings, samples or just concept.

Quotation                                                                       
Issue quotation within 3 days 
 Project kicks off upon receipt of deposit

Layout Assembly Drawing                                             
3 to 7 days for layout drawings

Detailed Design                                                             
Mold components with detail drawings.

Drawing Final Confirmation                                           
Drawings are finally confirmed by customer

Schedule                                                                         
Follow up the schedule

Mould Manufacture                                                         
Mould manufacture on schedule

Mould Trial Running and Samples               
Submitted                                                                       
Mould trial running on schedule, and Samples are submitted with a detailed inspection report

Sample Confirmation                                                     
After inspected final samples according to specifications customer make a confirmation.

Packing                                                                           
Tooling finished and packed   
                       
Delivery                                                                           
Paperwork and a CD of assembly drawings are sent to customer at the time of the shipment of the mould.